Administrative building “Jaunā Teika”
Gustava Zemgala gatve 78, Riga, LV-1039 The total area 18000 m²One of the most important construction projects implemented in 2017-2018 is the installation of the ventilated facade at the administrative building in Riga, at 8 k-1 Ropažu Street (“Jaunā Teika”). 1.
The set of completed works:
- designing of the load-bearing structure from thermoprofiles;
- design of the ventilated facade substructure;
- installation of load-bearing frame from thermoprofiles;
- Fermacell plate assembly;
- installing of ventilated facade, substructure, thermal insulation, ceramic tiles Paradyž;
- finishing with NEOBOND composite panels;
- installation of external window sills and decorative tin elements;
- plastering of the interior walls;
- laying of carpets in the Accenture office.
The volume of the implemented facade works – 9 517.71 m2
Deadlines for the performance of the works (including designing): 04.2017-05.2018
Contacts
Reaton finishing material shop working hours:
Mon-Fri: 9:00-18:00
Sat: 10:00-16:00
Sun: closed.
mc2 interior and finishing materials departments working hours:
Mon-Sat: 10:30-19:00
Sun: closed.